Busbar Installation in a Live Indoor Substation

Case StudiesConstructionDistribution Upgrades
1

Initial Site Survey and Risk Assessment

The first step was a thorough site survey to assess the layout of the substation, the existing equipment, and the clearances required for the new busbar installation. A detailed risk assessment identified the primary hazards, including proximity to live equipment and potential electrical arcs.
2

Shutdown Planning

While the entire substation could not be de-energized, certain sections were scheduled for temporary outages during installation. A carefully coordinated partial shutdown plan was developed, minimizing risks while maintaining grid reliability.
3

Engineering and Design

The design team collaborated with the manufacturer and supplier to finalize the engineering drawings for the busbar. These drawings detailed the exact routing, support locations, and connection points of the busbar system. The insulated busbars were chosen for their ability to reduce the required phase-to-phase clearances, making them ideal for the confined indoor space.
4

Safety Measures and Personnel Training

A comprehensive safety plan was developed, focusing on maintaining safe working distances from live equipment and ensuring the team had the appropriate training to work in a live substation. The installation crew underwent specialized training, including live substation protocols, the use of personal protective equipment (PPE), and equipotential bonding techniques.
1

Delivery and Handling

The busbars were delivered on pallets and stored temporarily at the substation. Due to the restricted space inside the substation, a telehandler was used to carefully transport the busbar sections from the storage area to the installation site.
2

Sectional Installation

The installation process was divided into smaller sections, with the busbar installed in 3-meter increments to ensure safety and minimize potential disruptions. Each section was carefully lifted into place using insulated lifting equipment.
3

Support and Mounting

Temporary supports were installed to hold the busbars in place while maintaining proper clearances from live components. The final mounting involved precise alignment to avoid any interference with existing energized equipment. The busbars were secured using insulated clamps and supports that could withstand thermal expansion and mechanical stress. A vast amount of supporting steel structures were installed (up to 40’ I-beams in multiple locations).
4

Joint Connections and Insulation Testing

Each joint connection between busbar sections was carefully bolted using insulated tools. After each section was installed, insulation resistance tests were conducted to verify the integrity of the epoxy resin insulation. High-potential testing was also carried out at specific intervals to ensure the system’s operational reliability. Testing was done to IEC 60137 standards.
5

Maintaining Live Equipment Safety

Throughout the installation process, special attention was paid to maintaining live working zones with insulated barriers to prevent accidental contact with energized components. Equipotential bonding was used to ensure the installation team worked within a safe environment, reducing the risk of electrical shock.