Electrical Systems for the Centre for Plant Health Renewal Project

Case StudiesConstructionEnergy Efficiency
1

Accelerated Project Planning and Coordination

To meet the compressed schedule, Sasco employed a lean construction approach, working closely with the project management team, architects, and other contractors. Weekly coordination meetings were scheduled to ensure milestones were met and dependencies between trades (such as HVAC and plumbing) were tightly managed. Sasco also developed a phased installation plan, ensuring work could progress in sections.
2

Increased Labor and Shifts

Recognizing that the tight schedule would require additional manpower, Sasco brought in extra crews and implemented double shifts where necessary. This approach helped ensure that work on critical systems, such as the geothermal energy wells and laboratory wiring, stayed on track despite the compressed timeline. Sasco’s skilled workforce also ensured high-standards were met despite the accelerated pace.
3

Proactive Materials Procurement

Sasco anticipated potential delays in sourcing specialized materials, particularly for the required distribution equipment, and energy-efficient systems. To mitigate this, we established close partnerships with suppliers and manufacturers early in the project and placed orders in advance. This strategy reduced the risk of delays and ensured the timely delivery of custom components such as the main distribution switchboard and transformers, and back-up power infrastructure.
4

Implementation of Prefabrication Techniques

Wherever possible, the Sasco utilized prefabrication. This involved assembling electrical components off-site, reducing installation time on-site and minimizing the impact of weather delays. Prefabrication was particularly useful for repetitive elements like conduit runs and pre-assembled lighting systems.
5

Enhanced Quality Control and Testing Protocols

Despite the time pressure, quality control remained a priority. Sasco established dedicated testing teams to verify installations as they were completed, ensuring that all systems – from power supplies to climate controls – met the stringent specifications required for a research facility. This approach minimized rework and ensured that any issues were identified and resolved in real-time.
6

Adapting to Sustainability Requirements

The Sasco electrical team worked closely with the sustainability consultants to ensure that all systems met LEED Gold standards. This included integrating energy-efficient lighting, advanced power-management systems, and environmentally-friendly practices such as geothermal energy integration. We ensured that the facility’s electrical systems contributed to its overall energy efficiency goals, helping reduce carbon emissions and lower operational costs long-term.